02 May 2019
Procon Readymix were appointed to supply 2,000m³ of C32/40 pump mix concrete with STRUX 90/40 fibres.
The inclusion of STRUX 90/40 acted as a replacement for A393 steel reinforcing mesh and over a three day period the inside of the composting shed took in excess of 800 cubic metres of concrete with the balance being used in the outer yard.
The contract was completed to the satisfaction of the customer and Grace Construction Products, who approved the mix design and monitored the dosing of the STRUX at the batching plant and the workability on site.